St. Armands Residents Association |
For information about flooding events on St. Armands Key, click here. |
July 28, 1998 | The City of Sarasota enters into an Interlocal agreement with Sarasota County to maintain all storm water systems located in the City of Sarasota. The city owns the system, but the county maintains it. |
2006 | A major stormwater improvement project was completed on St. Armands. A map of pump stations and baffle boxes, and a summary of the project details, can be viewed here. Not all of St. Armands Key drains by gravity alone. Previous to this project, there was a single pump station on St. Armands (PS 2005). This project rehabilitated that pump station, added four additional pump stations (for a total of five; each pump station has two pumps for a total of ten), added baffle boxes to collect debris and prevent it from reaching the pumps, and added two backup generators to power the pumps. |
November 7, 2023 | At a regular monthly meeting of the St. Armands Residents Association, the Sarasota County Director of Public Works, the City of Sarasota Director of Public Works, and the City Engineer were all present to answer questions about the flooding from Hurricane Idalia. The Sarasota County Director of Public Works gave this presentation. |
2023-2024 | We received additional information from the County Stormwater Operations Manager following the 2023 Hurricane Idalia and 2024 Invest 90L flooding events. |
June 28, 2024 | City news bulletin: (link)
|
July 17, 2024 | Email from Sarasota County Public Works Director to City Manager about the improvements completed over the last two years:
|
August 15, 2024 | Herald-Tribune article: Sarasota County is paving over paradise - and using our money to do it |
August 25, 2024 | Response from County Stormwater Operations Manager to a photo (see below) submitted by a St. Armands resident:
The reason why we had reported this particular storm drain was because Hurricane Debby was coming and a nearby resident had just sent this photo:
The County Stormwater Operations Manager personally came out that same day and reported the following:
Most of our storm drains lead to one of several below-grade "baffle boxes" that collect debris in "cages" before it can reach and clog/damage our stormwater pumps. The county has previously told us that they clean these out quarterly. The city is responsible for street sweeping. But, when you're out and about, if you notice debris or vegetation potentially clogging an individual storm drain, it needs to be reported. |
November 19, 2024 | Sarasota Citizen Action Network: Recommendations from hydrologist Stephen Suau in the wake of Tropical Storm Debby |
January 6, 2025 | Our Association email to Interim City Manager (who is also the city Public Works Director) and Deputy City Manager:
|
January 7, 2025 | Response from County Stormwater Operations Manager:
|
January 21, 2025 |
January 29, 2025 | Observer article: Town aims to upgrade resiliency of lift stations on island This article is about the Town of Longboat Key, not the City of Sarasota. But, it mentions a device that could benefit our stormwater pump control panels. Per the article:
|
March 28, 2025 | Joint Meeting of Sarasota County Commission and City of Sarasota Commission County Public Works Director recommends that the County ends the Interlocal Agreement; that the City of Sarasota takes over the maintenance of its stormwater management system. |
April 3, 2025 | We received responses to 21 questions that we sent to the County Director of Public Works and Stormwater Operations Manager. Televising Stormwater Pipes (1) The county was supposed to televise our stormwater pipes during the month of March. What were the results?
(2) Are photos or videos available?
(3) What technology and methodology was used to televise the drains, and were any robotics used like those at https://redzone.com/?
(4) Was the work limited to the St. Armands commercial district, or did it include residential streets as well?
(5) How many and what percentage of our storm drains got cameras inserted, broken down by commercial district and residential streets?
(6) What percentage of our underground pipes got televised, broken down by commercial district and residential streets?
(7) On January 4, 2024, the county told us that "Gravity stormwater pipeline joints are connected with gaskets or put together with Ram Neck (a tar-like material), and then the joints are wrapped with cloth. This process prevents the sand from entering the pipe; however, the joint can still allow water to flow into the pipe. Although this is not an acceptable practice for sanitary sewers that need sealed joints, it is for storm sewers." To what extent were the cameras able to effectively navigate these joints for the purpose of televising the drain pipes?
(8) What, if any, actions has the county taken or is planning to take as a result of the televising of St. Armands storm drains?
Storm Drain and Pipe Cleaning (9) People observed what looked like water jets being used to clean out storm drains. Was this done before or after televising them?
(10) In one case, it was observed that jetted water was inserted into one storm drain (drop), and was coming out of a storm drain (drop) across the street. This was where Fillmore Dr connects with St. Armands Circle. Is that a sign that the drain pipe was clogged since the water was coming back up on the street and not draining?
Backflow Preventers Background: It is our understanding that St. Armands Key has nine outfalls from which stormwater drains, or is pumped into, the bay. Four of these outfalls, the four that drain by gravity alone, are supposed to have Tideflex Duckbill Backflow Preventers on the ends of the outfalls. The other five outfalls do not have these because these are the outfalls that have check-valves (a different type of backflow prevention) built into the pump stations that feed them. On January 12, 2004, the county told us that our five pump stations "have check valves In the vault, which prevent the discharge pipes from backflowing into the wetwell. There is no need for Tideflex valves in these locations." (11) On January 4, 2024, the county told us that "we have four Tide Flex Valves on the system. They have all been inspected and are functioning". In February 2025, we took a photo (pasted at the bottom of this email) showing the Tideflex Duckbill Backflow Preventer located near the southern end of St. Armands in the vicinity of Fillmore Dr had broken off at the end of the outfall. When does the county plan to fix this?
(12) When does the county plan to inspect the other three outfall locations that are also supposed to have the Tideflex Duckbill Backflow Preventers to see if they might have also broken off?
(13) On January 9, 2004, the county told us that the check valves (backflow prevention) at Pump Station PS 2005 "are shot". What was the cause of this and how was this remedied?
(14) What condition are the check valves in at our other four pump station locations and what is the county's plan to repair or replace these to prevent failure during a future storm event?
Backup Generators (behind Fire Station and behind The Met) (15) On October 3, 2024, the county told us that "Both generator station fuel tanks suffered water infiltration during Helene. Emergency service was performed to clean and refuel the generators." What is the condition of those generators today, and what will be done to keep this same thing from happening in a future flood event?
Pump Station Control Panels (16) The county has told us that "All the new panels went underwater, and were shorted out again... Panels were inspected, and parts were ordered to replace appurtenances that came in contact with the saltwater." Can the panels be waterproofed to prevent this from happening again?
(17) The Longboat Observer printed an article on January 25, 2025 (https://www.yourobserver.com/news/2025/jan/29/town-resiliency-lift-stations/) saying that: "At those lift stations are electrical control panels that manage the amount of wastewater within that lift station. Currently, the control panels are fixed about one to two feet off of the ground" and that the town is looking at "Having them on a pole that can be elevated in the event of a possible storm". Can this be done with the St. Armands stormwater panels?
Use of Wood Mulch (18) After multiple recent flooding events and after televising our drains, what is the county's opinion of the city's continued use of wood mulch on St. Armands: is it not a problem, or should alternatives be investigated?
Temporary, Trailer-Mounted Pumps with Generators (19) It has been observed that the county and/or the city has been staging temporary, trailer-mounted pumps and generators on St. Armands so that they can be quickly activated should our permanent pumps fail. Is that the continued plan going forward?
(20) What triggers the decision to bring out the trailer-mounted pumps with generators?
(21) Do we, as the residents association, need to ask for this to be done each time, or can we trust that it will be done when appropriate?
|
April 15, 2025 | We received answers to six additional follow-up questions that we had sent to the County: (1) The county has not completed the work of televising our storm drains yet, even though they had previously indicated the work would be performed in March. When will the work be completed, and when will a report be provided to the city?
(2) The county mainly televised drains in the commercial district, not the residential district, despite there being homes that have been flooded four times in the last two years. See the map below. Nothing was televised in our hardest-hit northeast quadrant. Could you request that the county televise the entirety of Madison Dr from end-to-end, and also N Adams Dr, N Washington Dr, and John Ringling Blvd in the area all around the St. Armands Parking Garage, the St. Armands Key Lutheran Church, Pump Station PS 2005, Pump Station PS 7010, and Baffle Box BB# 5-10-65? (this has been the most flooded area from rain-only events)
(3) The county cleaned the drains BEFORE televising them. I suppose this makes sense if you're looking for damaged pipes. But we wanted to know how clogged the drains had gotten and how that could have impeded drainage. For any televising not yet performed, can that be done both BEFORE and after the cleaning? For drain pipes that have already been televised, was any record kept regarding the amount of mud and debris removed prior to televising?
(4) One of the answers says: "Compromised pipeline will be scheduled for repairs via direct bury, sectional liners, or whole liners from catchbasin to catchbasin." No detail was provided about whether or not any of this would be necessary at all, how much of each repair method would likely have to be done, and the timeframe for doing it. Could we get more information about this? Also, if any of this is necessary in the portion of the island that was televised, wouldn't that be an indicator that it might also be necessary in the portions of St. Armands that were not televised?
(5) One of our two backup generators is inoperable and apparently can not be repaired. It provides backup power to pump stations PS 7010 (east side of St. Armands) and PS 3015 (south side of St. Armands). These pump stations will no longer work in the event of a power outage. What is the timeline for this generator to be replaced?
(6) The county indicated that wood mulch was pulled out of the storm drains, but they did not make a recommendation about whether the city's continued use of wood mulch in the park and in our medians is a good idea. We would like to share this recommendation with residential and commercial property owners. What is the county's recommendation on this?
|
April 15, 2025 | Observer article: Sarasota County mulls stormwater turnover to the city |
April 18, 2025 |
May 28, 2025 | We sent these additional follow-up questions to the County Director of Public Works and we have never received an answer: Just over six weeks ago, on April 15, you sent answers to some of our stormwater questions... I'm hoping that six weeks is enough time for new updates to be available. Specifically: (1) You wrote: "the county didn’t complete the system by the end of March due to equipment failure. With the added pipeline request, it should be complete by mid May," The additional pipeline request referred to Madison Dr in the northeast quadrant. Has the televising of the pipes been completed? Can you provide an updated map of where this work was done? Here is the previous map: (2) Some residents have asked me if any pictures or videos of the televising of the pipes are available, and if anything was found that needs to be fixed. The April 18 County newsletter mentioned this. Is there anything notable that you can share about the results? (3) Regarding the inoperable backup generator at the Fillmore Parking Lot, you wrote: "The county is currently getting quotes and will expedite the process as quickly as possible. In the meantime a rental generator will be installed May 23rd and will remain in service until the new generator is installed." We've noticed that the rental generator is in place per the picture below--thank you. What is the status of the new replacement generator? (4) It is my understanding that there are nine outfalls on St. Armands, five of which serve our pump stations which have in-line backflow preventers in the pump chamber, and that the four outfalls that drain by gravity alone are supposed to have Tideflex Check Valves on the ends of the pipes. We sent the picture below showing that the Tideflex check valve had broken off one of these (southeast quadrant). I don't see the Tideflex check valves on the ends of the other gravity-fed outfalls. What is the status of getting the broken Tideflex check valve repaired? And can you explain why I don't see them on the other outfalls that drain by gravity alone? Thank you. I really appreciate your time and attention to these matters. Note: We have never received a reply to these four questions. |
June 5, 2025 | Statement from County Stormwater Operations Manager to ABC7 regarding recent heavy rainfall and water accumulation on St. Armands streets:
|
June 19, 2025 | Observer article: Resilience to floods may be on the way to St. Armands Key |
June 27, 2025 | Suncoast Searchlight article: Sarasota County officials downplayed flood risk. Tropical Storm Debby exposed their failures |
July 1, 2025 | Suncoast Searchlight article: Sarasota County stormwater crisis sparks major shakeup after public trust erodes Florida Trident article: Sarasota County stormwater crisis sparks major shakeup after public trust erodes |
July 2, 2025 | Observer article: New stormwater department to separate from Public Works |
July 7, 2025 | Sarasota County Press Release: Ben Quartermaine named the first Director of Stormwater Department
|
July 4, 2025 | LBK News article: New City Manager takes on budget, flooding, development |
July 9, 2025 | Florida Trident article: BREAKING: Sarasota Assistant County Administrator Resigns Amid Stormwater Fallout |